Fire Stations #1 and #3 Modernizations
Interior modernizations of Fire Stations number 1 and 3 starting late Spring 2025 with completion expected Spring 2026.
Project Status: Ongoing
Anticipated Timeline: Completion in Spring 2026
Point of Contact:
Tim Wisser, Municipal Properties Manager
248-364-6901
[email protected]
Revised 11/04/2025
Executive Hills Drive Asphalt Mill and Resurface
Road reconstruction, slimming the road to one lane in each direction, and adding pathways and lighting.
Project Status: Ongoing
Anticipated Timeline: Substantially Complete - Final Restoration Spring 2026
Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]
Revised 4/13/26
Tienken Road Asphalt Mill and Resurface
Asphalt mill and resurface.
Project Status: Ongoing
Anticipated Timeline: Substantially Complete - Final Restoration Spring 2026
Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]
Revised 4/13/26
Butler Road Asphalt Reconstruction
Full Road reconstruction and stormwater improvements.
Project Status: Ongoing
Anticipated Timeline: Substantially Complete - Final Restoration Spring 2026
Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]
Revised 4/13/26
Riverwalk Pathway
Project Status: Ongoing
Anticipated Timeline: Spring 2026 start date
Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]
Revised 11/04/2025
Birchfield & Patrick Henry Utility and Road Improvement
Water main replacement followed by road work in summer 2026.
Project Status: Ongoing
Anticipated Timeline: November 2025 - December 2026
Point of Contact:
Jason Deman, Public Utilities Manager
248-364-6912
[email protected]
Revised 04/13/2026
Shimmons/Squirrel Traffic Light
Traffic light installation at Shimmons and Squirrel Road.
Project Status: Ongoing
Anticipated Timeline: Anticipated Completion - May 2026
Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]
Revised 4/13/26
M-24 Lapeer Road Improvements
Asphalt and stormwater upgrades along Lapeer Road between I-75 and Harmon Road.
Project Status: Ongoing
Anticipated Timeline: Substantially Complete - Final Restoration Spring 2026
Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]
Revised 4/13/26
Centre Road - Innovation Drive Asphalt Mill and Resurface
Road reconstruction
Project Status: Ongoing
Anticipated Timeline: November 2026
Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]
Revised 4/13/26