Current Weather: 50Degrees Fahrenheit

Current Projects

Projected timelines are subject to change.

Fire Stations #1 and #3 Modernizations

Interior modernizations of Fire Stations number 1 and 3 starting late Spring 2025 with completion expected Spring 2026.

Project Status: Ongoing

Anticipated Timeline: Completion in Spring 2026

Point of Contact:
Tim Wisser, Municipal Properties Manager
248-364-6901
[email protected]

Revised 11/04/2025

Executive Hills Drive Asphalt Mill and Resurface

Road reconstruction, slimming the road to one lane in each direction, and adding pathways and lighting.

Project Status: Ongoing

Anticipated Timeline: Substantially Complete - Final Restoration Spring 2026

Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]

Revised 4/13/26

Tienken Road Asphalt Mill and Resurface

Asphalt mill and resurface.

Project Status: Ongoing

Anticipated Timeline: Substantially Complete - Final Restoration Spring 2026

Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]

Revised 4/13/26

Butler Road Asphalt Reconstruction

Full Road reconstruction and stormwater improvements.

Project Status: Ongoing

Anticipated Timeline: Substantially Complete - Final Restoration Spring 2026

Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]

Revised 4/13/26

Riverwalk Pathway

Project Status: Ongoing

Anticipated Timeline: Spring 2026 start date

Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]

Revised 11/04/2025

Birchfield & Patrick Henry Utility and Road Improvement

Water main replacement followed by road work in summer 2026.

Project Status: Ongoing

Anticipated Timeline: November 2025 - December 2026

Point of Contact:
Jason Deman, Public Utilities Manager
248-364-6912
[email protected]

Revised 04/13/2026

Shimmons/Squirrel Traffic Light

Traffic light installation at Shimmons and Squirrel Road.

Project Status: Ongoing

Anticipated Timeline: Anticipated Completion - May 2026

Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]

Revised 4/13/26

M-24 Lapeer Road Improvements

Asphalt and stormwater upgrades along Lapeer Road between I-75 and Harmon Road.

Project Status: Ongoing

Anticipated Timeline: Substantially Complete - Final Restoration Spring 2026

Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]

Revised 4/13/26

Centre Road - Innovation Drive Asphalt Mill and Resurface

Road reconstruction

Project Status: Ongoing

Anticipated Timeline: November 2026

Point of Contact:
Jason Hefner, Fleet & Roads Manager
248-364-6931
[email protected]

Revised 4/13/26